Timetable of piling locations

Updated monthly

The table below shows a monthly schedule of where we are carrying out piling for building the foundations for the world’s first T-pylons.

Activity NameParish Council/locationForecast Start
LD114 (Driven piling)Avonmouth15 June
LD113 (CFA piling)Avonmouth17 June
LD045R (CFA piling)North of Sandford20 June
LD065 (CFA piling)South of Kenn24 June
LD104 (CFA piling)Avonmouth27 June
LD064 (CFA piling)South of Kenn1 July
LD122 (CFA piling)Avonmouth4 July
LD063 (CFA piling)South of Kenn8 July
LD052 (CFA piling)Congresbury14 July
LD130 (Driven piling)Avonmouth31 August
*Please note these dates may change at short notice

Some nearby residents may hear noise and feel vibrations when we are carrying out piling. This will depend on how close you are to the site and the ground conditions and wind direction.

We recognise that our construction activity causes local impact. We are sorry if we cause any disturbance, we are working with our contractor to limit this as much as possible. The piling rig has been designed to minimise noise and vibrations and the hydraulic hammer is the most silenced on the market. We will not carry out piling over the weekends and we will limit piling to between the hours of 8am and 5pm.